Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
E) None of the above

Respuesta :

Otras preguntas

You kick a ball with a speed of 14 m/s at an angle of 51°. How far away does the ball land?
can you tell me what is a mandolin?
(1) Glen’s horse, Tipper, grazes lazily in his grassy.In sentence (1), what part of speech is "lazily"? (A)verb (B)adverb (C)adjective
What is the negative form of Elles y regardent la télé
1)simplify the expression (2x)^42)the perimeter of a rectangular is twice the sum of its length and its width. the perimeter is 16 meters and its length is 2 me
How do you find the constant of variation when y=-(2/3) and x=3
what is red snapper? could you help me?
A ball of mass 2 kg is kept on the hill of height 3 km. Calculate the potential energy possessed by it ?How can I get the potential energy ?
How do you find the constant of variation when y=-(2/3) and x=3
what is sugar art? could you help me?