The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

write 2 poems about fear.
blogy B Semester Exam Which piece of evidence best supports the hypothesis that the evolution of altruistic behavior is driven by kin selection? (1 point) O A h
Which of the following is a scientific observation about the bird pictured below? Scarlet ibis A. The pink feathers are especially beautiful. B.The long beak he
Let f(x)=x-6 and g(x) = 4x². Perform the function operation and then find the domain of the result. (f+g)(x)
Pls help I’ll brainlest asap I’ll add extra points
Formal Standard English and Standard English are the same things. true or false
What is 12 7/10 as a percent?
Animals like pigs with multiple stomachs are called:.
Find the quotient. (2 + 8k² − 9k) ÷ (k − 1) The quotient is
sue makes a bracelet she uses 8 1/4 inches of chain to make one bracelet how many whole bracelets can she make from a chain that is inches 57 1/2 long​