  • 23-04-2021
  • Business
contestada

What is the first phase of the project process?


A. Monitoring


B. Pre-Planning


C. Implementation


D. Planning

Respuesta :

tif21076 tif21076
  • 06-05-2021

Answer:Pre-planning

Explanation:

Answer Link
zlskfrum zlskfrum
  • 06-05-2021

Answer:

Explanation:

Implementation and Monitoring are latter phases of a project.  Pre-planning goes before Planning so the answer is B.

Answer Link

Otras preguntas

Where is the verb in this sentence: The air conditioning is making a funny noise.
Why did the bubonic plague cause people to turn away from the Church?
A food chain or food web can provide good information like _____.
Why did ethnic tension become such a severe problem in the Soviet Union and Yugoslavia?
what is the meaning of evil-doer a kenning word
Which of the following most likely requires intermolecular forces? A.a spider walking on the bottom of a leaf B.a rock maintaining its solid shape C.a koala usi
Which of these genes is not a part of the lac operon? A. operator gene B. promoter gene C. repressor gene
find the product -2x a(-4x b - 2x 3 + 5x)
Explain how Elizabeth I was able to bring a level of religious peace to England.
what were the connections between the Holy Roman Empire and the church?