An event that must occur in order for a party's duty to arise is called a(n) ________________.

Respuesta :

meerkat18
meerkat18 meerkat18
  • 05-12-2017
This is what they call condition precedent. The party's task to perform arise after a specific event happens. However, when the event never happens, the duty of the party to perform will never arise. The parties are discharged from the contract. 
Answer Link

Otras preguntas

ead this excerpt from Chapter 1 of I Know Why the Caged Bird Sings by Maya Angelou and answer the question. When I was three and Bailey four, we had arrived in
What was one effect of the trans-Saharan caravan trade during the thirteenth and fourteenth centuries
Most organisms contain the same codons. true false
What roles did Betty Friedan and Gloria Steinem play in the women’s movement?
graph of the function rule y=|5x|-2
How do biozones help scientists determine the age of a rock unit? a specific biozone can indicate a particular type of past environment. a biozone can help trac
Prove that u(n) is a group under the operation of multiplication modulo n.
read the following passage of the cay "in the morning, the air smells fresh and clean" what effect does the rainfall have on phillip and timothy? A) they are f
A store makes shirts and jackets to sell each shirt costs $4 to make and each jacket costs $25 to make
How much will you save per lb, by buying the least expensive? Round to the nearest cent. 2.5 lbs for $8.75 or 3 pounds for $9.75.