a task completed by 30 persons in 4 days. in how many days, the same will be completed by 40 persons?

Respuesta :

Plasmataco
Plasmataco Plasmataco
  • 25-11-2017
Basically to solve this you do:
Time1*Worker1=Time2*Worker2
Thus Time1=4, Worker1=30, Worker2=40
4*30=40*Time2
Time2=4*30/40
Time2=3 days
Answer Link

Otras preguntas

Eva Maria borrowed money from her father and agreed to pay him 4% simple annual interest. At the end of 7 years, Eva Maria owes $1736 in interest. What amount
Matt has a mass of 37 kg and skis down a hill with no friction or air resistance. The hill has an angle of 24 degrees. The free-body diagram is show below. a.
Where did most of what we know about the Phoenicians come from?
please help, easy geometry​
what is the most yummiest in the world​
when a car drives down a street what energy conversions are happening?
Among the third graders at Kensington Elementary School, 15 play kickball during recess and 18 play four square. Among the fourth graders, 11 play kickball and
What is the area of this picture​
20 POINTS!!!!!!!!!!!!!!!! How were the economies of ancient Mesopotamia, Egypt, and the Indus Valley similar? A. Most of their populations were enslaved. B.The
Convert into a trinomial: (7-8b)2